Chapter V

Underground Cable Systems and Installation

Red Seal Practice study guide with diagrams.

Underground Cable Systems and Installation

Underground Cable Installation — Layers and Installation Method Underground Cable Installation — Layers and Method Cross-section — Shielded three-phase cable Outer jacket Metallic armor Inner sheath Semi-conductive tape Insulation Conductor Trench installation — Side view Sand bed Warning tape Compacted backfill 0.6 m min. Installation steps 1. Trench excavation 2. Sand bed placement 3. Cable laying 4. Sand covering 5. Warning tape placement 6. Backfilling and compaction Note: The minimum bending radius must comply with the manufacturer's specifications (typically 12× the Ø). Legend Outer jacket Conductor Insulation Armor / sand Backfill

Chapter Introduction

Underground cable systems are an essential component of the electrical distribution network. As a powerline technician, you will be called upon to install, splice, terminate, and maintain these systems. This chapter covers all the knowledge required for the Red Seal exam, including cable types, installation methods, voltage calculations, Canadian Electrical Code (CE Code) rules, and safe work procedures.

Types of Underground Cables

Extruded Dielectric Cables

Extruded dielectric cables are the most common in modern underground distribution networks. They consist of an aluminum or copper conductor, a conductor semi-conductive shield, cross-linked polyethylene (XLPE) or ethylene-propylene rubber (EPR) insulation, an insulation semi-conductive shield, and a metallic or non-metallic sheath.

Key characteristics:

Conductor: aluminum (lightweight, economical) or copper (better conductivity, heavier)
Insulation: XLPE for service temperatures up to 90 °C, EPR for increased flexibility
Shield: copper tape or helical copper wires, required for voltages above 2 kV
Outer jacket: PVC, polyethylene, or metallic sheath depending on the application

Paper-Insulated Lead-Covered Cables (PILC)

Although less common in new installations, PILC cables still exist in many existing networks. They use oil-impregnated paper as the dielectric and require specialized splicing techniques.

Advantages: excellent thermal stability, long service life

Disadvantages: require complex joints, sensitive to moisture, require oil drainage

Gas-Insulated Cables

Used for very high voltages (225 kV and above), these cables use SF₆ (sulfur hexafluoride) as the insulator. Their installation is highly specialized and rarely encountered in standard distribution work.

Cable Identification

Marking and Labeling

Each underground cable must be identified according to the CE Code, Chapter V, Rule 5-102. Identification must include:

Conductor size (AWG or kcmil)
Insulation type (XLPE, EPR, etc.)
Voltage rating
Manufacturer's name
Year of manufacture

Colour Codes

Underground cable outer jackets use a standardized colour code:

Black: phase voltage (generally 28 kV or less)
Red: protection or emergency circuits
Blue: control or communication circuits
Yellow: gas-insulated or high-voltage cables

Voltage Calculations and Voltage Drop

Voltage Drop Formula

Voltage drop in an underground cable is calculated using the formula:

ΔV = √3 × I × L × (R cos φ + X sin φ) for three-phase systems

ΔV = 2 × I × L × (R cos φ + X sin φ) for single-phase systems

Where:

ΔV = voltage drop in volts
I = load current in amperes
L = cable length in kilometres
R = conductor resistance in Ω/km
X = cable reactance in Ω/km
cos φ = power factor

Calculation Example

Problem: A three-phase 500 kcmil aluminum cable with XLPE insulation is installed over a length of 800 m. The load current is 350 A with a power factor of 0.85. The conductor resistance is 0.120 Ω/km and the reactance is 0.150 Ω/km. Calculate the voltage drop.

Solution:

ΔV = √3 × 350 × 0.8 × (0.120 × 0.85 + 0.150 × sin(cos⁻¹ 0.85))

sin φ = √(1 - 0.85²) = √(1 - 0.7225) = √0.2775 = 0.527

ΔV = √3 × 350 × 0.8 × (0.102 + 0.079)

ΔV = √3 × 350 × 0.8 × 0.181

ΔV = 1.732 × 350 × 0.8 × 0.181

ΔV = 87.8 V

Percentage: (87.8 / 25,000) × 100 = 0.35% (acceptable, as it is less than 3%)

Table of Typical Resistances

Size (AWG/kcmil)Aluminum (Ω/km at 25 °C)Copper (Ω/km at 25 °C)
4 AWG1.3200.815
2 AWG0.8300.512
1/0 AWG0.5240.323
3/0 AWG0.3300.203
250 kcmil0.2240.138
500 kcmil0.1120.069

Installation Methods

Direct Burial

Direct burial is the most economical method for distribution cables. It involves burying the cable directly in a trench, without conduit.

Requirements according to the CE Code, Chapter V, Rule 8-200:

Minimum depth of 600 mm for distribution cables (up to 46 kV)
Minimum depth of 750 mm for transmission cables (above 46 kV)
Sand bed of 75 mm below and above the cable
Warning tape placed 300 mm above the cable
Backfill without stones or sharp debris

Conduit Installation

Conduit installation provides superior mechanical protection and facilitates future cable replacement.

Types of conduit:

Rigid PVC: most common, corrosion-resistant
Galvanized steel: for high-traffic areas or mechanical hazard zones
Fibreglass: for crossings under roads or railways

Installation requirements:

Minimum conduit diameter: 1.5 × the cable diameter for a single cable
Minimum bending radius: 12 × the cable diameter (for XLPE cables)
Spacing between supports: 1.5 m maximum
Minimum slope of 0.5% for drainage

Cable Pulling

Pulling cables through conduits requires special attention to avoid damaging the insulation.

Pulling tension calculation:

T = L × W × f

Where:

T = pulling tension in newtons (N)
L = conduit length in metres
W = cable weight in N/m
f = coefficient of friction (0.35 for PVC, 0.50 for steel)

Pulling tension limits:

Copper conductor: 70 N/mm² of cross-section
Aluminum conductor: 40 N/mm² of cross-section
Never exceed 4,500 N for a standard distribution cable

Pulling techniques:

Use a nylon or steel pulling rope
Apply a lubricant compatible with the cable jacket
Maintain a constant pulling speed (15 to 30 m/min)
Use a dynamometer to monitor tension

Splices and Joints

Types of Splices

Underground splices fall into two main categories:

Straight splices (joints): connect two cable lengths end to end

Tee splices (branch): connect a branch cable to a main cable

Components of a Splice

A properly made splice includes:

102.Connector: copper or aluminum compression sleeve
103.Semi-conductive shield reconstruction: semi-conductive tape
104.Insulation reconstruction: insulating tape or heat-shrink tubing
105.Metallic shield reconstruction: copper braid or tape
106.Outer protection: heat-shrink jacket or resin

Splice Procedure for XLPE Cable

Step 1: Preparation — cut the cable at a right angle, remove the outer jacket to the required length

Step 2: Remove the metallic shield and the insulation semi-conductive layer

Step 3: Clean the insulation with an appropriate solvent

Step 4: Install the connector by compression (use the correct die)

Step 5: Reconstruct the semi-conductive layer with semi-conductive tape

Step 6: Apply the splice insulation (tape or heat-shrink tube)

Step 7: Reconstruct the metallic shield

Step 8: Apply the outer protection

Important: The insulation semi-conductive layer must be removed without damaging the insulation. Use a special knife with an adjustable cutting depth.

Post-Splice Testing

After each splice, the following tests are required:

Continuity test: verify conductor continuity
Insulation test: measure insulation resistance with a megohmmeter (minimum 100 MΩ at 1 kV)
Voltage test: apply a test voltage (generally 3 × the rated voltage for 15 minutes)

Cable Terminations

Indoor Terminations

Indoor terminations are used in substations, transformer chambers, and enclosures. They can be dry-type or with shield termination.

Components:

Stress cone to reduce the potential gradient
Termination insulator
Outgoing connector
Arc protection

Outdoor Terminations

Outdoor terminations must withstand environmental conditions (rain, pollution, UV).

Types:

Porcelain terminations: traditional, used for voltages above 25 kV
Silicone terminations: lightweight, pollution-resistant
Heat-shrink terminations: easy to install, used up to 46 kV

Termination Installation Procedure

137.Remove the outer jacket to the specified length
138.Remove the metallic shield
139.Remove the insulation semi-conductive layer according to the provided template
140.Clean the insulation
141.Install the stress cone or heat-shrink tube
142.Attach the outgoing connector
143.Seal the end against moisture

Canadian Electrical Code Rules

Chapter V — Applicable Rules

The CE Code, Chapter V, contains the specific rules for underground installations. The main rules are:

Rule 8-200: Cable burial depth

600 mm minimum for distribution cables
750 mm for transmission cables
900 mm under vehicle driveways

Rule 8-202: Mechanical protection of cables

Cables buried directly in the ground must be protected by a layer of sand or screened earth
A warning tape must be installed 300 mm above

Rule 8-204: Spacing between cables

Minimum 75 mm between cables of different circuits
Minimum 300 mm between power cables and communication cables

Rule 8-206: Underground conduits

Conduits must be watertight
Minimum drainage slope of 0.5%
Conduits must be sealed at the ends

Rule 8-208: Manholes

Maximum spacing of 100 m between manholes
Minimum dimensions according to the number and size of cables

Table of Burial Depths

Type of InstallationVoltageMinimum Depth
Direct burial≤ 46 kV600 mm
Direct burial> 46 kV750 mm
Conduit≤ 46 kV600 mm
Conduit> 46 kV750 mm
Under vehicle drivewayAny voltage900 mm
Under railwayAny voltage1,200 mm

Thermal Considerations

Cable Ampacity

The ampacity of an underground cable depends on several factors:

Ambient soil temperature (generally 20 °C)
Soil thermal resistivity (generally 1.0 °C·m/W)
Burial depth
Grouping with other cables
Soil type (sand, clay, rock)

Correction Factors

Correction factor for soil temperature:

Soil TemperatureCorrection Factor
10 °C1.07
20 °C1.00
25 °C0.95
30 °C0.89
35 °C0.84

Correction factor for grouping:

Number of CablesSpacing 0 mSpacing 0.3 mSpacing 0.6 m
20.800.900.95
30.700.850.92
40.600.800.90
50.550.780.88

Soil Thermal Resistivity

Soil TypeThermal Resistivity (°C·m/W)
Dry sand2.5
Wet sand0.7
Clay1.0
Topsoil0.8
Rock1.5

Fault Location

Location Methods

Time Domain Reflectometer (TDR) method: sends a pulse and measures the reflection time to determine the distance to the fault. Accuracy of ±1% of total length.

Wheatstone bridge method: compares the resistances of two conductors to locate a solid fault. Accuracy of ±2%.

Step voltage method: applies a pulsed voltage and measures the potential gradient at the ground surface. Accuracy of ±0.5 m.

Location Procedure

187.Isolate the cable: disconnect both ends
188.Test the insulation: megohmmeter to confirm the fault
189.Identify the fault type: solid, intermittent, high resistance
190.Pre-location: TDR or bridge
191.Precise location: step voltage or acoustic detector
192.Confirmation: excavation and visual verification

Safety During Underground Work

Specific Hazards

Electrical hazard: underground cables can remain energized even after disconnection (residual capacitance). Always verify the absence of voltage with an appropriate detector.

Fire hazard: PILC cables contain oil that can ignite. Have an appropriate fire extinguisher nearby.

Gas hazard: underground chambers can contain methane, hydrogen sulfide, or oxygen deficiency. Test the atmosphere before entering.

Collapse hazard: trenches must be shored or have safe slopes according to occupational health and safety regulations.

Mandatory Safety Procedures

200.Work permit: required for all underground work
201.Utility locating: locate all underground services before excavating
202.Voltage verification: use a voltage detector suitable for the network voltage
203.Grounding: cables must be grounded and short-circuited before cutting
204.Ventilation: chambers must be ventilated for 15 minutes before entry
205.Attendant: one person must remain outside during work in a chamber

Common Pitfalls to Avoid

Pitfall 1: Confusing the burial depth for direct burial (600 mm) with that for conduits under driveways (900 mm). The CE Code, Chapter V, Rule 8-200, specifies different depths depending on the type of installation.

Pitfall 2: Forgetting the correction factor for soil temperature when calculating ampacity. A cable installed in soil at 30 °C must be derated by 11% from its rated value.

Pitfall 3: Using the single-phase voltage drop formula for a three-phase system. The three-phase formula uses √3, not 2.

Pitfall 4: Neglecting the insulation semi-conductive layer during splicing. An improperly removed or reconstructed semi-conductive layer causes partial discharges and premature failure.

Pitfall 5: Confusing copper and aluminum resistance. Aluminum has a resistance approximately 1.6 times higher than copper for the same size.

Pitfall 6: Forgetting the warning tape at 300 mm above the cable. This requirement of Rule 8-202 is often tested on the exam.

Pitfall 7: Using a lubricant that is not compatible with the cable jacket. Some lubricants can attack PVC or polyethylene.

Pitfall 8: Not accounting for the minimum bending radius during pulling. A radius that is too tight damages the insulation invisibly.

Pitfall 9: Confusing the tests required after splicing. The voltage test must be performed at 3 × the rated voltage, not at the rated voltage.

Pitfall 10: Entering an underground chamber without testing the atmosphere. Gas accumulation is a deadly hazard that is often underestimated.

Summary

Underground cable systems are a critical component of electrical distribution networks. To succeed on the Red Seal exam, you must master:

219.Cable types: XLPE, EPR, PILC, and their distinctive characteristics
220.Voltage drop calculations: single-phase and three-phase formulas, correction factors
221.Installation methods: direct burial, conduits, pulling, with regulatory depths and spacings
222.Splicing and termination techniques: procedures, components, verification tests
223.CE Code, Chapter V rules: Rules 8-200 to 8-208, depths, protections, spacings
224.Thermal considerations: ampacity, correction factors, soil resistivity
225.Fault location: TDR, bridge, and step voltage methods
226.Safety procedures: voltage verification, grounding, chamber atmosphere

Key points to remember:

Standard depth of 600 mm for distribution, 750 mm for transmission
Warning tape mandatory at 300 mm above the cable
Minimum bending radius of 12 × the cable diameter
Voltage test after splicing at 3 × the rated voltage
Temperature correction factor: 0.89 at 30 °C
Maximum pulling tension: 70 N/mm² for copper, 40 N/mm² for aluminum
Always check the atmosphere before entering an underground chamber

Exam tips:

Read questions about depths carefully — they often include traps about exceptions
Memorize the voltage drop formulas and correction factors
Questions about splices often focus on the order of steps and common errors
Safety questions are frequent — know the mandatory procedures by heart
Use the tables in this chapter as a quick reference during your review

This chapter prepares you for both the theoretical and practical questions on the exam. Mastering these concepts, combined with your practical experience, will allow you to approach the exam with confidence.

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free