Chapter IV

Structural Steel Erection

Red Seal Practice study guide with diagrams.

Steel Structure Erection

Steel Structure Erection — Column Placement and Guying Steel Structure Erection — Column Placement and Guying Ground Column base Column base Column A Guy line Tag line Column B (lifting in progress) Crane Rule: guy before releasing the hook Key components: • Column — W-shape • Guy line — cable • Base plate • Anchor bolts Rotation Finished level Column height

Introduction to Steel Structure Erection

Steel structure erection is one of the core activities of the ironworker (generalist) trade. This task involves assembling, on the job site, the prefabricated structural steel elements — beams, columns, joists, bracing, and decking — to form the load-bearing structure of a building or civil engineering project. The Red Seal exam requires a complete mastery of the procedures, calculations, and standards that govern this activity.

This chapter covers the fundamental principles, lifting methods, bolted and welded connections, tolerances, load calculations, and Canadian regulatory requirements. You must be able to apply this knowledge in practical situations and answer typical exam questions.

Applicable Standards and Codes

CSA S16 — Design of Steel Structures

CSA S16 (Canadian Standards Association) is the primary reference for the design and calculation of steel structures in Canada. It defines the requirements for materials, connections, tolerances, and assembly methods. Although the ironworker does not design the structure, you must understand the principles of this standard to interpret plans and specifications.

Key points of CSA S16 that you need to know:

Clause 22 : Requirements for bolts and welds
Clause 23 : Fabrication and erection tolerances
Clause 26 : Connections — bolt and weld resistance
Clause 27 : Members in flexure (beams)
Clause 28 : Members in compression (columns)

CSA W59 — Welded Steel Construction

CSA W59 (Welding — Steel Structure Welding Rules) specifies the requirements for welding steel structures. It covers processes, welder qualifications, joint types, electrodes, and quality control. The ironworker must know welding symbols and inspection requirements.

CSA S16.1 — Tolerances

CSA S16.1 defines the allowable tolerances for the fabrication and erection of steel structures. These tolerances are essential for ensuring the alignment and stability of the structure. The main tolerances to remember:

ElementAllowable Tolerance
Column plumbness± 1/500 of height (max 25 mm)
Beam alignment± 6 mm from axis
Bearing level± 3 mm
Column spacing± 3 mm from plan
Beam deflectionL/360 (span divided by 360)

Site Preparation

Reading Plans and Shop Drawings

Before any work begins, the ironworker must read and interpret the erection plans and shop drawings. These documents indicate:

The dimensions and positions of each element
The types of connections (bolted, welded)
Part numbers and marks
General notes and specific specifications
Design loads and reactions at supports

Erection plans use standardized symbols. You must know the meaning of the following symbols:

Circle with a center point : column
Rectangle with a diagonal : beam
Triangle : bracing
Dashed line : element to be installed later

Verifying Foundations and Anchor Bolts

Before starting erection, the ironworker must verify:

35.Anchor bolt position : anchor bolts must be positioned according to specified tolerances (generally ± 3 mm)
36.Level of bearing plates : bearing plates must be level
37.Concrete strength : concrete must have reached the specified strength (generally 70% of nominal strength)
38.Surface cleanliness : bearing surfaces must be free of debris, ice, or water

Receiving and Storing Materials

Steel elements are delivered to the site by truck. The ironworker must:

Verify that pieces match the delivery slips
Visually inspect elements for damage (deformations, cracks, corrosion)
Store elements on wooden blocking to prevent contact with the ground
Protect elements from weather conditions if necessary

Lifting and Rigging Equipment

Cranes — Types and Capacities

The choice of crane depends on reach, height, weight of elements, and site conditions. The main types of cranes used:

Crane TypeTypical ReachTypical CapacityApplication
Crawler crane30 to 150 m50 to 500 tonsLarge projects, rough terrain
Mobile crane on wheels20 to 80 m20 to 200 tonsUrban sites, frequent moves
Telescopic crane15 to 60 m10 to 100 tonsSmall and medium projects
Tower crane30 to 100 m5 to 50 tonsHigh-rise buildings

Calculating Lifting Capacity

The ironworker must verify that the crane can safely lift each element. The basic calculation is:

Crane capacity ≥ (Weight of element + Weight of rigging) × Safety factor

The safety factor is generally 1.25 for lifting operations. The weight of rigging (slings, hooks, shackles) must be included in the calculation.

Example : A beam weighs 4,500 kg. The slings weigh 150 kg. The minimum required capacity is:

(4,500 + 150) × 1.25 = 5,812 kg = 5.8 tons

The crane must have a capacity of at least 5.8 tons at the required reach and height.

Slings and Lifting Accessories

Slings are essential elements for lifting. Common types:

Wire rope slings : strong, durable, but rigid
Chain slings : flexible, abrasion-resistant, but heavy
Synthetic web slings : lightweight, flexible, but susceptible to cuts

The sling angle is a critical factor. The tighter the angle, the greater the tension in each sling. The formula for calculating tension in each sling:

T = (P / n) × (1 / sin θ)

Where:

T = tension in each sling (kg)
P = weight of the load (kg)
n = number of slings
θ = angle between the sling and the horizontal

Example : A 2,000 kg load is lifted by 2 slings at a 60° angle.

T = (2,000 / 2) × (1 / sin 60°) = 1,000 × 1.155 = 1,155 kg per sling

At 30°, the tension would be: (2,000 / 2) × (1 / sin 30°) = 1,000 × 2 = 2,000 kg — double. The minimum recommended angle is 60°.

Erection Procedures

Erecting Columns

Columns are the first elements to erect. The typical procedure:

74.Positioning : the column is lifted and positioned over the anchor bolts
75.Alignment : the column is aligned vertically using a level or transit
76.Temporary fixing : temporary bracing is installed to hold the column in position
77.Final bolting : nuts are tightened to the specified torque
78.Verification : plumbness is checked and adjusted if necessary

Columns are generally bolted to base plates using anchor bolts. Tightening must be done using the turn-of-nut method or to the specified torque.

Erecting Beams

Beams are lifted after columns. The procedure:

82.Preparation : beams are fitted with slings and guide lines
83.Lifting : the beam is lifted to the required height
84.Positioning : the beam is positioned on seats or bearing plates
85.Bolting : connections are bolted, first temporarily, then permanently
86.Release : slings are removed once the beam is secured

Important rule : never release the load until the beam is secured with at least two bolts per connection.

Bracing

Bracing provides lateral stability to the structure. It is installed as soon as possible after erecting columns and beams. Types of bracing:

X-bracing : two crossed diagonals
K-bracing : one diagonal and one vertical
V-bracing : two diagonals forming a V

Bracing is generally bolted to gusset plates welded onto columns and beams.

Decking

Decking (or metal floor deck) is installed after the main structure. It serves as a working surface and horizontal diaphragm. Decking is attached to beams using self-drilling screws or pins. Requirements:

Screws must be installed at the specified spacing (generally 300 mm on supports, 150 mm on edges)
Decking must be aligned and fastened before being used as a working surface
Edges must be protected with guardrails if necessary

Bolted Connections

Types of Bolts

Bolts used in steel structures are standardized according to ASTM A325 or ASTM A490. A325 bolts are carbon steel, while A490 bolts are high-strength alloy steel.

TypeDiameter (mm)Minimum Tensile Strength (MPa)Application
A32512.7 to 25.4825Standard connections
A49012.7 to 25.41,040High-strength connections

Bolt Tightening

Bolt tightening is critical to connection performance. Three tightening methods are recognized:

105.Torque method : tightening to a specified torque using a torque wrench
106.Turn-of-nut method : snug tightening, then rotating the nut a specified amount (generally 1/2 turn or 1/3 turn)
107.Direct tension indicator method : using washers with tension indicators

The tightening torque is calculated using the formula:

T = K × D × P

Where:

T = tightening torque (N·m)
K = friction coefficient (generally 0.2 for A325 bolts)
D = nominal bolt diameter (m)
P = required bolt tension (N)

Example : A 19 mm (0.019 m) A325 bolt must be tensioned to 125 kN (125,000 N).

T = 0.2 × 0.019 × 125,000 = 475 N·m

Washers and Nuts

Washers are used to distribute the load and protect the surface. Requirements:

Hardened washers are required under the nut for A325 and A490 bolts
Washers must be the correct size (inside diameter slightly larger than the bolt diameter)
Nuts must conform to ASTM A563

Inspection of Bolted Connections

Inspection of bolted connections includes:

Verifying the type and diameter of bolts
Verifying tightening (marking bolts after tightening)
Verifying the number of visible threads (at least 2 threads beyond the nut)
Verifying the presence of washers

Welded Connections

Welding Processes

Welding processes used for steel structures:

SMAW (Shielded Metal Arc Welding) : manual process, used for site work
GMAW (Gas Metal Arc Welding) : semi-automatic process, used for long welds
FCAW (Flux-Cored Arc Welding) : semi-automatic process, used for site work

Types of Welds

The most common types of welds:

Fillet weld : joins two perpendicular or inclined surfaces
Groove weld : joins two surfaces in the same plane
Plug weld : fills a hole in one piece to connect it to another

The size of a fillet weld is measured by the length of its leg. Strength is calculated based on the throat of the weld (distance between the root and the face).

Welding Symbols

The ironworker must be able to read welding symbols according to AWS A2.4. Elements of the symbol:

Reference line : horizontal line on which the symbol is placed
Arrow : points to the weld
Basic symbol : indicates the type of weld (triangle for fillet weld, etc.)
Dimensions : size and length of the weld
Contour : shape of the weld surface

Welder Qualification

Welders must be qualified according to CSA W47.1 (Certification of Welding Companies). Qualification includes:

A practical test on a representative assembly
Visual inspection and non-destructive testing
A valid certification for a specified period

Tolerances and Quality Control

Erection Tolerances

Erection tolerances are defined in CSA S16.1. The main tolerances:

ParameterTolerance
Column plumbness± 1/500 of height (max 25 mm)
Horizontal beam alignment± 6 mm
Bearing level± 3 mm
Column spacing± 3 mm
Beam deflectionL/360

Quality Control

Quality control includes:

Visual inspection : checking alignment, connections, welds
Non-destructive testing : ultrasonic, radiographic, magnetic particle testing for critical welds
Document verification : material certificates, qualification reports

Site Safety

Fundamental Safety Rules

Safety is paramount in steel structure erection. Fundamental rules:

Wearing a fall arrest harness : mandatory from 3 m (10 ft) in height (according to provincial regulations, but the Red Seal requires knowledge of the principles)
Lifeline : installed before starting work at height
Guardrails : installed on the edges of floors and openings
Safety nets : used when guardrails are not possible

Construction Site Regulations

The Canada Occupational Health and Safety Regulations apply to construction sites. Key points:

Section 2.10.1 : Hard hat mandatory
Section 2.10.2 : Safety footwear mandatory
Section 2.10.3 : Fall arrest harness mandatory above 3 m
Section 2.10.4 : Guardrails required above 1.8 m

Lifting and Rigging

Safe lifting rules:

Never stand under a suspended load
Use standardized lifting signals (hand signals, flags, radio)
Inspect slings before each use
Respect the rated capacity of equipment

Practical Calculations for the Ironworker

Load Calculations

The ironworker must be able to calculate loads on elements. Typical loads:

Dead load : self-weight of the structure and permanent elements
Live load : weight of people, materials, and temporary equipment
Wind load : wind pressure on the structure

The total load on a beam is:

Q_total = Q_dead + Q_live

Deflection Calculation

The deflection of a beam is calculated using the formula:

Δ = (5 × w × L⁴) / (384 × E × I)

Where:

Δ = deflection (mm)
w = uniformly distributed load (N/mm)
L = span (mm)
E = modulus of elasticity (200,000 MPa for steel)
I = moment of inertia (mm⁴)

Example : A 6 m (6,000 mm) beam supports a load of 10 kN/m (10 N/mm). The moment of inertia is 50 × 10⁶ mm⁴.

Δ = (5 × 10 × 6,000⁴) / (384 × 200,000 × 50 × 10⁶)

Δ = (5 × 10 × 1.296 × 10¹⁵) / (3.84 × 10¹³)

Δ = 6.48 × 10¹⁶ / 3.84 × 10¹³

Δ = 1,687 mm

This deflection is excessive. The allowable deflection is L/360 = 6,000/360 = 16.7 mm. A stiffer beam is required.

Stability Calculation

Column stability is verified by calculating the slenderness ratio:

λ = KL / r

Where:

λ = slenderness ratio
K = effective length factor (1.0 for a column pinned at both ends)
L = column length (mm)
r = radius of gyration (mm)

The maximum allowable slenderness ratio is 200 for main columns.

Common Pitfalls to Avoid

Here are the most common mistakes made by Red Seal exam candidates:

214.Confusing the standards : CSA S16 is for design, CSA W59 for welding, CSA S16.1 for tolerances. Don't mix them up.
215.Forgetting the safety factor in lifting calculations. The 1.25 factor is mandatory.
216.Neglecting the sling angle : an angle below 60° significantly increases tension in the slings.
217.Ignoring tolerances : erection tolerances are strict. A column out of tolerance must be corrected before continuing.
218.Confusing A325 and A490 bolts : A490 bolts have higher strength but must not be used with ordinary washers.
219.Forgetting temporary bracing : the stability of the structure during erection is critical. Never erect more than two storeys without bracing.
220.Not checking anchor bolts : anchor bolts must be verified before erecting columns.
221.Tightening bolts in the wrong order : tightening must be done from the center toward the ends to avoid distortion.
222.Ignoring weather conditions : wind, rain, and ice affect safety and work quality.
223.Not wearing personal protective equipment : the harness is mandatory from 3 m in height.

Summary

Steel structure erection is a complex activity that requires in-depth knowledge of standards, procedures, and calculations. Key points to remember:

Standards : CSA S16 (design), CSA W59 (welding), CSA S16.1 (tolerances)
Preparation : reading plans, checking anchor bolts, receiving materials
Lifting : calculating crane capacity, minimum sling angle of 60°, safety factor of 1.25
Erection : columns first, then beams, then bracing, then decking
Connections : A325 and A490 bolts, tightening using the torque method or turn-of-nut method
Tolerances : plumbness ± 1/500, alignment ± 6 mm, level ± 3 mm
Safety : harness above 3 m, guardrails above 1.8 m, never under a suspended load

The ironworker must be able to apply these principles in real situations and answer exam questions accurately. Practicing calculations and knowing the standards are essential for success.

Review Questions

235.What is the plumbness tolerance for a column 8 m in height?
Answer: ± 1/500 × 8,000 = ± 16 mm (max 25 mm)
237.A 22 mm A325 bolt must be tensioned to 150 kN. What is the tightening torque?
Answer: T = 0.2 × 0.022 × 150,000 = 660 N·m
239.What is the tension in each sling if a 3,000 kg load is lifted by 4 slings at a 45° angle?
Answer: T = (3,000 / 4) × (1 / sin 45°) = 750 × 1.414 = 1,060 kg
241.What is the allowable deflection for a beam with a 9 m span?
Answer: L/360 = 9,000 / 360 = 25 mm
243.What is the maximum allowable slenderness ratio for a main column?
Answer: 200

These questions represent the type of problems you will encounter on the exam. Practice solving these calculations quickly and accurately.

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free