Chapter IV

Setup, Assembly, and Disassembly of Cranes

Red Seal Practice study guide with diagrams.

Installation, Assembly, and Disassembly of Cranes

Chapter Introduction

The installation, assembly, and disassembly of a mobile crane constitute the most critical phase of the work cycle. More than 60% of fatal mobile crane incidents occur during these operations, according to data from the Canadian Standards Association. This chapter covers the fundamental principles, safe procedures, stability calculations, and regulatory requirements that every Red Seal exam candidate must master.

1. Fundamental Principles of Stability

1.1 Centre of Gravity and Stability

Crane stability is based on the balance between the overturning moment (load + boom) and the stabilizing moment (crane weight + counterweights). The combined centre of gravity (crane + load) must always remain within the support polygon.

The support polygon is the area bounded by the crane's points of support. For a crawler crane, this is the rectangle formed by the tracks. For a truck crane with outriggers deployed, it is the rectangle formed by the four outriggers.

Fundamental overturning moment formula:

Overturning moment (OM) = Load weight (L) × Horizontal distance (D)

Stabilizing moment (SM) = Crane weight (W) × Distance from centre of gravity to tipping point (d)

The stability condition requires that: SM ≥ 1.5 × OM (minimum safety factor of 1.5 for mobile cranes per CSA Z150).

1.2 Factors Affecting Stability

FactorEffect on StabilityConsideration
WindIncreases overturning momentReduce load according to load chart
Uncompacted soilOutrigger settlementUse cribbing/crane mats
SlopeShifts centre of gravityLevel crane to ±1%
Centrifugal forceIncreases dynamic loadReduce swing speed
Dynamic load (hoisting)10–25% load increaseImpact factor per CSA Z150
TemperatureAffects hydraulic viscosityCylinder stabilization time

1.3 Ground Bearing Pressure Calculation

The pressure exerted by outriggers on the ground must be calculated to prevent settlement:

Pressure (kPa) = Outrigger load (kN) ÷ Pad area (m²)

Example: A crane exerts 180 kN on one outrigger. The pad measures 0.6 m × 0.6 m.

Area = 0.6 × 0.6 = 0.36 m²

Pressure = 180 ÷ 0.36 = 500 kPa

If the soil bearing capacity is 300 kPa, a larger pad is required:

Required area = 180 ÷ 300 = 0.6 m²

Minimum dimensions = √0.6 = 0.775 m × 0.775 m

Rule of thumb: Typical soil bearing capacities are 100–200 kPa for clay soil, 300–500 kPa for compacted gravel soil, and 1000+ kPa for concrete.

2. Site Preparation for Installation

2.1 Ground and Work Area Assessment

Before any installation, the operator must perform a site assessment in accordance with CSA Z150-16, Article 4.3. This assessment includes:

27.Visual inspection of the ground to detect soft spots, recent backfill, and cavities
28.Verification of underground utilities (gas lines, electrical cables, water mains) — contact local authorities
29.Slope evaluation — the crane must be leveled to within 1% (1 cm per metre)
30.Identification of overhead obstacles — power lines, structures, trees
31.Verification of maneuvering space — the boom swing area must be clear

Minimum clearance from power lines (Canadian Electrical Code, Part I, Chapter V, Rule 8-200):

Line VoltageMinimum Distance
0 to 750 V3 m
750 V to 75 kV4.5 m
75 kV to 250 kV6 m
250 kV and above6 m + 10 mm per kV above 250 kV

2.2 Cribbing and Crane Mats

Cribbing (outrigger pads) must be used systematically under outriggers when the ground is not reinforced concrete. Requirements:

Minimum area: calculated based on ground bearing pressure (see Section 1.3)
Minimum thickness: 50 mm of steel or 200 mm of treated hardwood
Positioning: centred under the jack, flat, with no gaps
Surface area: pads must be large enough to fully support the outrigger float

Crane mats: For very soft ground, use timber mats (typically 1.2 m × 1.2 m × 100 mm) stacked in a crisscross pattern to distribute the load over a larger area.

2.3 Crane Leveling

Leveling is performed using the outrigger jacks and a spirit level or digital inclinometer. The maximum tolerance is 1% (1 cm/m) in all directions.

Leveling procedure:

44.Deploy outriggers to their maximum extension
45.Extend the jacks until the wheels no longer touch the ground (25–50 mm clearance)
46.Check longitudinal and transverse level
47.Adjust jacks individually
48.Re-check after counterweights are installed

3. Boom Assembly

3.1 Boom Types and Their Characteristics

Boom TypeAdvantagesDisadvantagesTypical Applications
Telescopic boomQuick setup, no loose partsLimited reachUrban job sites, general lifting
Lattice boomLong reach, lightweightLong assembly time, multiple partsLarge job sites, wind turbines
Lattice boom with fly jibMaximum reachReduced stability, complex assemblyHigh-rise work
Offset jibExtended reachCapacity reductionWindow installation, HVAC

3.2 Lattice Boom Assembly Procedure

Lattice boom assembly follows a precise sequence:

54.Position the crane on a level surface, outriggers deployed
55.Install counterweights according to the assembly chart (typically 50–100% of total counterweight)
56.Assemble boom sections on the ground, on horses
57.Align pins — pins must be inserted without excessive force
58.Install hoist cables — the cable must be reeved through the sheaves according to the manufacturer's diagram
59.Verify electrical connections for load and angle limiters
60.Erect the boom using the gin pole or hydraulic lift cylinder
61.Install pendants — correct length according to the chart
62.Final verification — boom angle, cable tension, alignment

Critical point: Connecting pins must be spring pins or cotter pins, never replaced with ordinary bolts.

3.3 Telescopic Boom Assembly

The telescopic boom is generally assembled in a horizontal or slightly inclined position:

66.Verify crane level before any extension
67.Deploy the boom at the minimum recommended angle (typically 0–5°)
68.Extend sections one at a time, checking alignment
69.Verify limiters — the load limiter must be calibrated after each configuration change
70.Test operation — raise/lower, swing, extend/retract without load

Golden rule: Never extend the telescopic boom with a suspended load if the load chart prohibits it. Some configurations allow extension with a reduced load (tele-scoping under load), but only according to manufacturer specifications.

4. Counterweights and Balancing

4.1 Types of Counterweights

TypeTypical MassAdvantagesDisadvantages
Steel counterweights (plates)2–10 t per plateDurable, preciseHeavy to handle
Concrete counterweights3–15 t per blockLess expensiveBulky
Hydraulic (retractable) counterweightsIntegratedNo handling requiredLimited mass
Trailer-mounted counterweights10–30 tHigh capacityRequires trailer

4.2 Counterweight Installation

Counterweight installation procedure:

77.Consult the manufacturer's assembly chart to determine the number and position of counterweights
78.Install counterweights in the specified order (typically from inside to outside)
79.Verify locking — each counterweight must be mechanically locked
80.Never exceed the specified counterweight capacity
81.Document the installed configuration

Common error: Installing more counterweight than necessary to improve stability. This can actually reduce stability by increasing the overturning moment on the boom side (the additional counterweight increases total weight and may exceed the structural capacity of the slewing ring).

4.3 Calculating Required Counterweight

The required counterweight depends on the boom configuration and the maximum anticipated load:

Required counterweight (C) = (OM - SM_without_counterweight) ÷ Counterweight_distance

Where:

OM = Maximum anticipated overturning moment (load × radius)
SM_without_counterweight = Stabilizing moment of the crane without counterweight
Counterweight_distance = Distance from the counterweight centre of gravity to the tipping point

Example: A crane has a maximum overturning moment of 1200 kN·m. The stabilizing moment without counterweight is 600 kN·m. The counterweights are located 4 m from the tipping point.

C = (1200 - 600) ÷ 4 = 150 kN = 15 tonnes

5. Crane Disassembly

5.1 General Disassembly Procedure

Disassembly follows the reverse order of assembly, but with additional precautions:

95.Remove the load and position the boom at the recommended disassembly angle
96.Lower the boom onto horses if necessary
97.Remove counterweights in the reverse order of installation
98.Retract outriggers only after lowering the boom
99.Inspect components for wear or damage
100.Secure loose parts for transport

5.2 Lattice Boom Disassembly

Critical points when disassembling a lattice boom:

Lower the boom to the minimum angle (typically 0–5°) before removing pendants
Use horses to support boom sections
Remove pins in the reverse order of assembly
Mark sections to facilitate reassembly
Check cable condition — cables must be wound onto reels, never folded

5.3 Transporting Components

ComponentTransport MethodRequirements
Boom sectionsFlatbed truckMinimum 4-point tie-down
CounterweightsFlatbed truck or trailerSecuring, weight verification
CablesCable reelsProtection from moisture
Pins and accessoriesBoxes or containersInventory, corrosion protection
OutriggersSecured to craneJacks retracted, mechanical locking

Transport regulations: The transport of crane components is subject to the Transportation of Dangerous Goods Regulations if loads exceed regulatory limits. Over-dimensional loads require special permits.

6. Pre-Use Checks

6.1 Pre-Assembly Inspection

Before assembly, the operator must inspect:

114.Structure — cracks, deformation, corrosion on boom sections
115.Pins and shafts — wear, deformation, presence of safety pins
116.Cables — broken wires, corrosion, deformation, diameter reduction
117.Sheaves — groove wear, free rotation
118.Hydraulic cylinders — leaks, damaged rods
119.Limiters — proper operation, intact seals

6.2 Post-Assembly Functional Test

After complete assembly, perform the following tests:

122.No-load hoist test — raise/lower the hook through the full travel
123.Swing test — full rotation left and right
124.Radius variation test — boom raise/lower
125.Limiter test — verify load and angle limiter activation
126.Emergency test — emergency stop, emergency descent

CSA Z150-16, Article 5.2 requirement: Every crane must undergo an inspection and functional test after each assembly, before being put into service.

6.3 Hoist Cable Inspection

The hoist cable must be inspected according to the following criteria:

DefectRejection Criteria
Broken wires6 broken wires over a length of 6 diameters, or 3 broken wires in one strand
Diameter reductionMore than 7.5% reduction from nominal diameter
CorrosionVisible corrosion with pitting
DeformationKinks, loops, crushing, elongation
OverheatingDiscoloration due to heat

7. Environmental Conditions and Human Factors

7.1 Wind and Weather Conditions

CSA Z150-16, Article 4.4.2, requires work stoppage when:

Wind speed exceeds 32 km/h (20 mph) for normal operations
Wind speed exceeds 20 km/h for large surface area loads (panels, containers)
Wind speed exceeds the manufacturer's specified limit for the configuration in use

Wind load area calculation: Effective wind load (F) = 0.5 × ρ × V² × A × Cd

Where:

ρ = air density (1.225 kg/m³)
V = wind speed (m/s)
A = projected area (m²)
Cd = drag coefficient (0.8–1.2 depending on shape)

Rule of thumb: A 2 m × 6 m load (12 m²) exposed to a 40 km/h wind experiences a force of approximately 1.1 kN, which can represent 5–10% of the crane's capacity.

7.2 Temperature and Freezing Conditions

Extreme low temperatures: hydraulic cylinders can freeze, cables become more brittle
Frozen ground: may appear stable but thaws under outriggers
Cold wind: increases operator fatigue risk
Precipitation: ice on the boom increases weight and wind exposure

7.3 Human Factors

The human factor is responsible for more than 80% of incidents. The main factors:

151.Fatigue — assembly operations are physically demanding
152.Production pressure — never compromise safety to save time
153.Communication — use a qualified signal person, two-way radios
154.Competence — assembly must be supervised by a qualified person
155.Independent verification — a second set of eyes to check critical connections

8. Regulatory and Standards Requirements

8.1 Applicable Canadian Standards

StandardTitleMain Content
CSA Z150-16Safety of Mobile CranesDesign, operation, and maintenance requirements
CSA Z248-17Tower CranesRules for tower cranes (if applicable)
CSA B149.1Natural Gas and Propane Installation CodeIf the crane operates on propane
Canadian Electrical Code, Part I, Chapter VElectrical SafetyPower line clearances
Canada Occupational Health and Safety Regulations (Part II of the Canada Labour Code)General requirementsEmployer and employee obligations

8.2 Operator Obligations per CSA Z150-16

The operator must:

161.Verify inspection and maintenance certificates for the crane
162.Perform a daily inspection before use
163.Consult the manufacturer's manual for assembly procedures
164.Never exceed the rated capacity shown on the load chart
165.Report any defects to their supervisor immediately
166.Refuse to operate if safety conditions are not met

8.3 Required Documentation

DocumentContentRetention
Manufacturer's manualAssembly procedures, load chartsOn board the crane
Inspection logDaily, weekly, annual inspectionsMinimum 3 years
Annual inspection certificateInspection by a qualified inspectorPosted in the cab
Lift planFor critical liftsOn site
Work permitAuthorization to operateOn site

9. Emergency Procedures

9.1 Hydraulic Failure During Assembly

In the event of hydraulic failure during assembly:

172.Do not attempt repairs under load
173.Lower the load using the emergency descent system
174.Secure the boom with mechanical supports
175.Evacuate the area under the load
176.Contact the supervisor and maintenance service

9.2 Imminent Overturn

If the crane begins to tip:

179.Lower the load immediately if possible
180.Reduce the radius (retract the boom)
181.Evacuate the area — do not attempt to save the crane
182.Shut off the engine and engage the swing brake
183.Call for emergency services if there are injuries

9.3 Power Line Contact

In the event of power line contact:

186.Stay in the cab — do not get out
187.Move the boom away from the line if possible
188.Alert authorities — have the power shut off
189.Only exit after confirmation that the power is off
190.If the cab is on fire: jump clear of the crane, feet together, avoiding simultaneous contact with the crane and the ground

10. Load Charts and Configurations

10.1 Understanding the Load Chart

The load chart indicates the maximum capacity for each configuration. Items to check:

194.Boom length — each added section changes capacity
195.Boom angle — capacity increases with angle
196.Radius — horizontal distance from the centre of rotation to the hook
197.Counterweight — capacity depends on installed counterweight
198.Outriggers — deployed or retracted
199.Fly jib — installed or not

10.2 Simplified Load Chart Example

50 t crane, outriggers deployed, full counterweight:

Radius (m)10 m Boom20 m Boom30 m Boom
350.0 t35.0 t25.0 t
535.0 t28.0 t20.0 t
822.0 t20.0 t15.0 t
1016.0 t15.0 t12.0 t
158.0 t7.0 t
204.0 t4.0 t

Interpolation: For a radius of 7 m with a 20 m boom, the capacity is between 28 t (at 5 m) and 20 t (at 8 m). Linear interpolation: 28 - [(7-5)/(8-5)] × (28-20) = 28 - 5.33 = 22.67 t.

10.3 Capacity Reduction Factors

ConditionReduction Factor
Wind > 20 km/h (large surface area load)20–30%
Wind > 32 km/hWork stoppage
Uneven ground (> 1%)Prohibited
Outriggers partially deployedPer manufacturer's chart
Temperature > 40 °C10% reduction
Load with side windReduction based on surface area

11. Communication and Signaling

11.1 Standard Hand Signals

Hand signals must follow CSA Z150-16, Annex B:

SignalDescription
Hoist loadForearm vertical, index finger pointing up, circular motion
Lower loadForearm vertical, index finger pointing down, circular motion
SwingArm horizontal, index finger pointing in direction of swing
TravelArm bent, palm up, motion toward the body
StopArm horizontal, palm down, abrupt motion
Emergency stopBoth arms crossed above the head

11.2 Radio Communication

Use two-way radios on a dedicated channel
Confirm each command by repeating it
Use clear, standardized language
When in doubt, stop the operation

Summary

The assembly, installation, and disassembly of a mobile crane require rigorous technical mastery and strict compliance with Canadian standards. The essential points to remember:

217.Stability is based on moment balance — the minimum safety factor is 1.5 per CSA Z150-16
218.Leveling must be within 1% in all directions
219.Cribbing is mandatory on non-concrete ground — calculate ground bearing pressure
220.Counterweights must be installed according to the manufacturer's chart — never exceed specifications
221.Boom assembly follows a precise sequence — pins must never be forced
222.Post-assembly checks are mandatory — inspection and functional test before service
223.Wind limits operations — 32 km/h maximum, 20 km/h for large surface area loads
224.Electrical clearances are defined by the Canadian Electrical Code, Part I, Chapter V, Rule 8-200
225.Documentation must be complete and current — manual, logs, certificates
226.Communication is essential — standardized signals, radios, qualified signal person

Common Pitfalls to Avoid

228.Confusing overturning moment and stabilizing moment — the overturning moment is the product of the load and its horizontal distance, not vertical.
229.Forgetting the impact factor — during hoisting, the dynamic load can be 10–25% higher than the static load.
230.Neglecting soil bearing capacity — apparently stable ground can settle under outriggers. Always calculate ground bearing pressure.
231.Installing too much counterweight — this can damage the slewing ring and reduce stability in certain configurations.
232.Using ordinary bolts to replace boom pins — this is prohibited and dangerous.
233.Forgetting to verify limiters after assembly — limiters must be calibrated for each configuration.
234.Disassembling the boom without horses — the boom can deform under its own weight.
235.Ignoring wind conditions — wind speed must be measured at boom height, not at ground level.
236.Not checking underground utilities — a gas line punctured by an outrigger can cause an explosion.
237.Confusing radius and boom length — radius is the horizontal distance, not the boom length.
238.Forgetting the human factor — fatigue and production pressure are major causes of incidents.
239.Not documenting configurations — each assembly configuration must be recorded for future reference.
240.Using non-standardized signals — only CSA Z150-16 signals are accepted.
241.Not checking the boom angle after assembly — the angle directly affects capacity.
242.Skipping the daily inspection — the pre-use inspection is mandatory and non-negotiable.

Ready to test this chapter?

Practice with exam-aligned questions and timed simulations.

Start Practicing Free