Concrete Formwork and Placement
Red Seal Practice study guide with diagrams.
Formwork and Concrete Placement
Introduction to Formwork and Concrete Placement
Formwork is a temporary or permanent mold designed to contain fresh concrete, give it its shape, dimensions, and surface texture, and support it until it has gained sufficient strength to support itself. Concrete placement, on the other hand, encompasses all operations from the delivery of fresh concrete to its consolidation and curing. For the Construction Craft Worker (CCW), mastering these operations is essential, as they represent a significant portion of tasks on construction sites across Canada.
Concrete is a composite material consisting of cement, water, fine aggregates (sand) and coarse aggregates (gravel or crushed stone), and admixtures. Its strength is expressed in megapascals (MPa) at 28 days, according to CSA A23.1 (Concrete: Constituent Materials and Execution of Work) and CSA A23.2 (Test Methods and Standard Practices for Concrete). Formwork must be designed and constructed to resist the lateral pressure of fresh concrete, which is a horizontal force acting on the mold walls.
Fundamental Principles of Formwork
Role and Requirements of Formwork
Formwork must satisfy four main requirements:
Types of Formwork
| Type | Material | Typical Use | Advantages | Disadvantages |
|---|---|---|---|---|
| Timber formwork | Plywood, boards | Small elements, curved shapes | Versatile, economical | Limited lifespan, possible deformation |
| Metal formwork | Steel, aluminum | Walls, columns, repetitive elements | Reusable, smooth surface | Heavy, expensive to purchase |
| Insulated formwork (ICF) | Expanded polystyrene + lintels | Foundation walls, residential buildings | Built-in insulation, lightweight | Higher cost, requires finishing |
| Lost formwork | Cardboard, precast concrete, fiber | Columns, foundations, buried elements | No stripping required | Not reusable |
| Slip formwork | Steel, timber | Silos, chimneys, elevator cores | Continuous construction | Requires specialized crew |
Lateral Pressure of Fresh Concrete
Lateral pressure (Ω) is the horizontal pressure exerted by fresh concrete on the formwork walls. It depends on several factors:
The theoretical maximum pressure is calculated using the hydrostatic formula:
Ω = ρ × g × h
Where:
Example: For a 3 m high wall, with concrete at 2400 kg/m³:
Ω = 2400 × 9.81 × 3 = 70,632 Pa ≈ 70.6 kPa
This pressure is maximum at the bottom of the formwork and decreases linearly toward the top. Shores and ties must be sized to resist this pressure, with an appropriate safety factor according to CSA S269.1 (Formwork for Concrete) and CSA S269.2 (Steel Formwork).
Formwork Design and Construction
Formwork Materials
Formwork plywood (phenolic) is the most common material for the contact surface with concrete. It is available in 1.22 m × 2.44 m (4 ft × 8 ft) panels with thicknesses of 12.7 mm (1/2 in), 15.9 mm (5/8 in), and 19.05 mm (3/4 in). The plywood must be classified according to CSA O121 (Douglas Fir Plywood) for formwork use.
Members (studs, stiffeners) are typically dimensional lumber (2×4, 2×6, 2×8) or engineered beams (I-joists, LVL). They transfer loads to the support system.
Ties (anchor rods) are threaded steel rods that pass through the formwork to hold the two opposite faces at the correct distance. They are spaced according to load calculations and are removed after stripping. Holes left by ties must be filled with mortar or an approved repair product.
Shores (vertical supports) and braces (inclined supports) hold the formwork in vertical and horizontal position. They must be securely anchored to resist lateral loads (wind, vibration, impact).
Wall Formwork Construction Steps
Special Formwork
Column formwork: Square or rectangular columns use metal or plywood formwork with column clamps spaced vertically. Round columns use cardboard tubes (lost formwork) or segmented metal forms. Lateral pressure in a column is particularly high due to the height of fresh concrete.
Beam and slab formwork: Beams are formed with bottoms and sides supported by shores. Slabs use a table system (pre-assembled panels) or traditional formwork with joists, stringers, and plywood decking. Formwork tables are efficient for repetitive slabs, as they can be moved with a crane.
Slip formwork: Used for continuous vertical structures (silos, chimneys, pylons), slip formwork is raised hydraulically or mechanically as concrete is placed. The raising speed must be synchronized with the concrete setting time to avoid deformations.
Concrete Placement
Preparation Before Pouring
Before placing concrete, several checks are necessary:
Placement Methods
| Method | Equipment | Advantages | Disadvantages |
|---|---|---|---|
| **Concrete bucket** | Crane + bucket | Versatile, precise | Requires a crane, limited output |
| **Concrete pump** | Stationary or mobile pump | High output, difficult access | High cost, risk of blockage |
| **Chute** | Mixer truck | Simple, economical | Limited reach, segregation risk |
| **Hopper and hose** | Hopper + flexible hose | Free-fall control | Requires setup |
| **Wheelbarrow / cart** | Wheelbarrow, concrete cart | Small volumes, interior work | Labour-intensive |
Placement Rules
Concrete Vibration
Vibration is the process of consolidating fresh concrete to eliminate trapped air bubbles and ensure complete encapsulation of reinforcement. It is essential for achieving dense, strong concrete.
Types of vibrators:
Vibration rules:
Construction Joints
A construction joint is a contact surface between two successive concrete pours. It must be designed and prepared to ensure adequate bonding between the two concretes.
Types of joints:
Construction joint preparation:
Calculations and Tolerances
Concrete Quantity Calculation
The quantity of concrete required is calculated by volume (m³). For a simple element (wall, slab, beam), the volume is:
V = L × W × H
Where:
Example: A slab measuring 10 m × 5 m × 0.15 m:
V = 10 × 5 × 0.15 = 7.5 m³
You should order approximately 5 to 10% additional concrete to compensate for losses, irregularities, and overflows.
Tie Quantity Calculation
The number of ties required for a wall formwork is calculated based on lateral pressure and the capacity of each tie.
Example: A wall 3 m high and 10 m long, with a lateral pressure of 70.6 kPa. Each tie has a capacity of 20 kN (20,000 N).
The total force on the formwork is:
F = Ω × A = 70,600 Pa × (3 m × 10 m) = 2,118,000 N
The number of ties required is:
N = F / capacity = 2,118,000 / 20,000 = 106 ties
In practice, ties are spaced on a regular grid (for example 600 mm × 600 mm), which gives:
N = (10 / 0.6) × (3 / 0.6) = 17 × 5 = 85 ties (rounded up to 90 with edges).
Dimensional Tolerances
CSA A23.1 defines the following tolerances for concrete elements:
| Element | Tolerance |
|---|---|
| Section dimensions (width, height) | ±10 mm |
| Reinforcement position | ±10 mm |
| Vertical alignment of walls | ±10 mm per 3 m of height |
| Slab level | ±10 mm |
| Position of openings and inserts | ±10 mm |
| Finished surface (flatness) | 3 mm under a 3 m straightedge |
Stripping and Curing
Stripping Time
Formwork must only be stripped when the concrete has reached sufficient strength to support its own weight and construction loads. The minimum required strength is generally 70% of the specified 28-day strength, but it may vary according to specifications.
Stripping time depends on:
| Ambient Temperature | Walls (stripping) | Slabs (stripping) |
|---|---|---|
| 20 °C | 24 to 48 hours | 7 to 14 days |
| 10 °C | 48 to 72 hours | 10 to 21 days |
| 5 °C | 72 to 96 hours | 14 to 28 days |
Important: Premature stripping can cause cracking, deformation, or structural collapse. Late stripping can make formwork removal difficult and damage the concrete surface.
Concrete Curing
Curing is the process of maintaining concrete at adequate temperature and humidity during the setting and hardening period. It is essential for:
Curing methods:
| Method | Description | Minimum Duration |
|---|---|---|
| **Water spraying** | Continuous moistening of the surface | 7 days |
| **Wet burlap** | Covering the surface with maintained-wet fabrics | 7 days |
| **Curing membrane** | Application of a film-forming product (curing compound) | 7 days |
| **Steam** | Steam curing for precast elements | 12 to 24 hours |
| **Thermal curing** | Heating concrete by resistance or steam | Variable |
The minimum curing duration is 7 days at a temperature above 10 °C, according to CSA A23.1. In cold weather, curing must be extended or the concrete must be protected with insulation.
Safety and Regulations
Site Safety
Working with formwork and concrete presents several hazards:
Applicable Canadian Standards
| Standard | Title | Application |
|---|---|---|
| **CSA A23.1** | Concrete: Constituent Materials and Execution of Work | Requirements for concrete, formwork, placement, and curing |
| **CSA A23.2** | Test Methods and Standard Practices for Concrete | Strength, slump, and air content testing |
| **CSA S269.1** | Formwork for Concrete | Design and construction of timber formwork |
| **CSA S269.2** | Steel Formwork | Design and construction of steel formwork |
| **CSA O121** | Douglas Fir Plywood | Plywood classification for formwork |
| **CSA A3000** | Cement | Classification and requirements for cements |
| **Canada Occupational Health and Safety Regulations** | Part II | General safety requirements on federal worksites |
Pitfalls to Avoid
Summary
Formwork and concrete placement are essential skills for the Construction Craft Worker. The key points to remember for the Red Seal exam are:
By mastering these concepts and practicing the calculations, you will be well prepared to succeed on the formwork and concrete placement section of the Red Seal exam. Good luck!
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free