Vertical and Elevated Finishing
Red Seal Practice study guide with diagrams.
Vertical and Elevated Finishing
Chapter Introduction
Vertical and elevated finishing is a specialized area of the concrete finishing trade. Unlike horizontal slabs, vertical elements (walls, columns, beams) and elevated elements (floor slabs, bridge decks, parking garage slabs) present unique challenges: concrete must be placed against formwork, compacted by vibration, and then finished under conditions where access is limited and gravity works against you. This chapter covers all the knowledge required for the Red Seal exam, including formwork techniques, placement, vibration, mechanical troweling, architectural finishes, and safety requirements.
Fundamental Principles of Vertical Concrete
Behavior of Fresh Concrete in Vertical Elements
Fresh concrete is a thixotropic material: it flows under stress (vibration) and stiffens at rest. In vertical formwork, the lateral pressure of fresh concrete is the critical parameter. It depends on:
Maximum lateral pressure is calculated using the ACI 347 formula (adapted to the Canadian context):
P = γ × h (maximum hydrostatic pressure)
Where:
In practice, the pressure never exceeds full hydrostatic pressure. For concrete with normal setting time (temperature 20 °C), the effective pressure can be reduced according to the rate of rise. The following table gives approximate lateral pressures for concrete with a 100 mm slump, internally vibrated:
| Rate of Rise (m/h) | Concrete Temperature | Maximum Lateral Pressure (kPa) |
|---|---|---|
| 1.0 | 20 °C | 48 |
| 1.0 | 10 °C | 58 |
| 2.0 | 20 °C | 72 |
| 2.0 | 10 °C | 88 |
| 3.0 | 20 °C | 95 |
| 3.0 | 10 °C | 115 |
Golden rule: the colder the concrete and the faster the formwork is filled, the higher the lateral pressure. Poorly braced or improperly designed formwork can blow out under this pressure.
Formwork for Vertical Elements
Formwork must resist lateral pressure, maintain the geometry of the element, and produce a surface that meets finishing requirements. Common formwork types:
Tie rods are steel elements that pass through the formwork to resist lateral pressure. Their spacing is calculated based on the allowable load of the tie and the estimated lateral pressure. For a 4,000 lb (17.8 kN) tie, with a pressure of 50 kPa and a vertical spacing of 600 mm, the maximum horizontal spacing is:
Horizontal spacing = Allowable load / (Pressure × Vertical spacing)
Horizontal spacing = 17,800 N / (50,000 Pa × 0.6 m) = 0.59 m → 550 mm in practice
Snap ties are ties with break-off cones that snap off at stripping, leaving a hole to be patched. Water stops are used for foundation walls where watertightness is required.
Placing Concrete in Vertical Elements
Placement Methods
Concrete must be placed in vertical formwork in successive horizontal layers, never in a single pour. The thickness of each layer must not exceed 600 mm (2 feet). This limitation allows:
Placement methods:
Free-fall rule: the free fall of concrete into vertical formwork must not exceed 1 meter (3 feet) to prevent segregation. Beyond that, use a drop chute or hopper.
Vibrating Vertical Concrete
Vibration is essential for vertical elements. It removes air bubbles, ensures proper cover over reinforcement, and fills all corners of the formwork. Two types of vibrators:
Internal vibrator parameters:
| Parameter | Recommended Value |
|---|---|
| Frequency | 12,000 to 14,000 vibrations/min |
| Needle diameter | 25 to 75 mm depending on the element |
| Radius of action | 6 to 10 times the needle diameter |
| Vibration time per insertion | 5 to 15 seconds |
| Distance between insertions | 1.5 times the radius of action |
Correct vibration procedure:
Signs of adequate vibration:
Over-vibration: over-vibration causes segregation, accumulation of mortar on the surface, and loss of strength. It is particularly damaging in vertical elements where mortar rises along the reinforcement.
Finishing Vertical Surfaces
Types of Vertical Finishes
The finish of a vertical element depends on its final use. The following table summarizes the types of finishes and their characteristics:
| Type of Finish | Description | Typical Use |
|---|---|---|
| **As-struck (form finish)** | Surface as produced by the formwork, without touch-up | Foundation walls, hidden structural elements |
| **Rubbed** | Surface smoothed by manual or mechanical rubbing after stripping | Exposed interior walls |
| **Broom finish** | Surface textured with a broom, for traction | Stair treads, ramps |
| **Sandblasted** | Surface textured by sand projection | Architectural facades |
| **Bush-hammered** | Surface hammered to expose aggregates | Decorative walls |
| **Acid-etched** | Surface etched with acid to expose aggregates | Architectural elements |
| **Plastered** | Application of a finishing mortar | Repair, leveling |
Stripping and Curing Vertical Elements
Stripping must not be done before the concrete has reached sufficient strength to support its own weight and stripping stresses. The general rule:
Stripping must be done without impact or forceful prying. Use wooden wedges or stripping jacks to separate the formwork from the concrete.
Curing vertical elements: curing is critical because vertical surfaces dry faster than horizontal surfaces (no puddle of water to compensate for evaporation). Curing methods:
Minimum curing duration: 7 days at 20 °C, or until the concrete reaches 70% of its specified strength.
Elevated Elements: Slabs and Floors
Formwork and Shoring for Elevated Slabs
The formwork of an elevated slab must support the weight of fresh concrete, reinforcement, workers, and equipment, as well as dynamic placement loads. Formwork components:
Shore spacing: calculated based on total load and the load-bearing capacity of the shores. For a 200 mm thick slab:
With shores of 30 kN capacity, spaced at 1.2 m in both directions, each shore supports 1.44 m² × 7.6 kN/m² = 10.9 kN — acceptable.
Reshoring rule: after stripping, shores must be replaced under the slab (reshoring) to support construction loads from upper floors. Reshoring must be done as soon as possible after stripping.
Placing Concrete in Elevated Slabs
Concrete is placed in strips or sections, starting from the side farthest from the pump or crane. The placement sequence must avoid creating concentrated loads on any area of the formwork.
Slab thickness: checked using a depth probe or laser level. The typical tolerance is ± 10 mm for a 200 mm slab.
Finishing Elevated Slabs
Finishing an elevated slab follows the same principles as for a slab on grade, but with additional constraints:
Finishing sequence for an elevated slab:
Attention to joints: elevated slabs require contraction joints (saw-cut or formed) spaced at 20 to 30 times the slab thickness. For a 200 mm slab, maximum spacing of 6 m. Joints must be saw-cut within 6 to 24 hours after finishing, before shrinkage causes cracking.
Architectural Vertical Finishes
Architectural Concrete
Architectural concrete is concrete whose surface is intended to remain permanently visible. Requirements are more stringent than for ordinary structural concrete:
Common architectural concrete defects:
| Defect | Cause | Prevention |
|---|---|---|
| **Honeycomb** | Insufficient vibration, concrete too dry | Vibrate systematically, increase slump |
| **Surface air bubbles** | Insufficient vibration, un-oiled formwork | Vibrate longer, oil the formwork |
| **Mortar (laitance)** | Excess water, over-vibration | Control slump, avoid over-vibration |
| **Color variation** | Cement variation, uneven curing | Standardize sources, uniform curing |
| **Form lines** | Misaligned joints, deformed formwork | Check alignment, reinforce formwork |
Repairing Surface Defects
Repairs must be made with a repair mortar compatible with the existing concrete. The mortar must have:
Repair procedure:
Safety for Vertical and Elevated Work
Working at Heights
Work on elevated formwork, scaffolding, or aerial work platforms presents fall hazards. Safety requirements:
Concrete-Specific Hazards
Formwork Stability
Formwork must be inspected by a competent person before each pour. Checkpoints:
Useful Calculations and Conversions
Calculating Concrete Volume for a Wall
Volume (m³) = Length (m) × Height (m) × Thickness (m)
Example: wall 12 m long, 3 m high, 200 mm thick:
V = 12 × 3 × 0.2 = 7.2 m³
Calculating the Number of Ties
Number of ties = (Length / Horizontal spacing) × (Height / Vertical spacing)
For the wall above, with 550 mm horizontal spacing and 600 mm vertical spacing:
N = (12 / 0.55) × (3 / 0.6) = 21.8 × 5 = 109 ties
Pressure Conversion
1 MPa = 1,000 kPa = 145 psi
1 kPa = 20.9 lb/ft²
Calculating the Load on a Shore
Load per shore (kN) = Surface load (kN/m²) × Shore spacing (m) × Shore spacing (m)
For a load of 7.6 kN/m² and shores at 1.2 m × 1.2 m:
Load = 7.6 × 1.2 × 1.2 = 10.9 kN
Applicable Standards and Codes
Vertical and elevated finishing work is governed by several Canadian standards:
| Standard | Subject | Key Points |
|---|---|---|
| **CSA A23.1/A23.2** | Concrete: constituents and execution of work | Requirements for concrete, placement, curing |
| **CSA A23.3** | Design of concrete structures | Strength, reinforcement, durability |
| **CSA S269.1** | Concrete formwork | Design, allowable loads, inspection |
| **CSA S269.3** | Slip forms | Specific requirements for slip forms |
| **CSA Z462** | Workplace electrical safety | Relevant if electrical equipment is used |
| **Canada Labour Code** | Occupational health and safety | General employer obligations |
Key points of CSA A23.1 for vertical elements:
Pitfalls to Avoid
Summary
Review Questions (Exam-Style)
(Answer: b — approximately 50 kPa according to the table for 1.5 m/h at 15 °C)
(Answer: c — 150 mm)
(Answer: b — 20,000 / (60,000 × 0.6) = 0.556 m)
(Answer: c — 7 days)
(Answer: c — 20 to 30 times the thickness: 250 × 30 = 7,500 mm = 7.5 m)
This chapter covers all the essential knowledge for the Red Seal exam in vertical and elevated finishing. Master the pressure calculations, vibration procedures, and curing requirements — these are the most frequently tested topics.
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free